FNL Runway 15-33 Widening Project 


 

 

Next Meeting: May 13, 2026 3PM-4PM
Location: FNL Administration Building, 4900 Earhart Rd. Loveland CO 80538

Virtual Option: Zoom-  https://us06web.zoom.us/j/83953581244?pwd=02wUgiXyRWrkrbaYRNXcb0SwyJMNap.1

 

*Project Meetings are scheduled every two weeks on a Wednesday at 3:00PM

 

Safety Management System (SMS) / Safety Risk Management (SRM) Panel

Meeting #1 – April 24, 2026
Meeting #2 – TBD

The Safety Management System (SMS) / Safety Risk Management (SRM) Panel will convene on April 24, 2026. This is a closed, invitation-only session led by representatives from the FAA Airports District Office (ADO), FAA Flight Standards District Office (FSDO), FAA Air Traffic Organization (ATO), and Airport staff.

During this session, panel participants will review project elements to identify potential hazards, assess associated risks, and determine appropriate mitigation strategies to support safe project execution.

A summary of outcomes and any resulting action items will be distributed via email by the end of day Friday and posted to this webpage the following week.

 

 

FNL Runway 15-33 Widening Project

Cost: $20,675,982   

Description: This project will widen Runway 15-33 from 100-feet to a total width of 150-feet. New structural runway pavement will be constructed adjacent to the existing pavement section with new runway lighting, signage, and edge drains. The five existing connector taxiways adjacent to the east side of the runway will be modified to tie into the new runway edge. After completion of paving, a seal coat will be applied to all runway pavement, followed by new runway pavement markings. 

Projects Summary:

  • Widen runway 15/33 from 100 ft to 150 ft to meet current FAA standards.
  • Correct Geometry of Taxiway connectors.
  • Widen blast pads.
  • Extend runway grooving.
  • Install new underdrains.
  • Replace electrical systems, including lighting, signage and PAPIs.

Project Impacts:

  • Temporary reduction in operational capacity for the duration of construction. For a detailed breakdown of anticipated operational impacts, please refer to the Informational Packet below.

Important Documents:

 

Questions?

Call: 970-962-2580   

Email: FNLCustomerService@cityofloveland.org

Last Updated: 05/06/2026